Your company is reviewing a project with estimated labor costs of $20.20 per unit, estimated raw material costs of $36.18 a unit, and estimated fixed costs of $20,000 a month. Sales are projected at 42,000 units over the one-year life of the project. What would the total variable costs be if the actual variable costs per unit are 5% higher than estimated and the actual sales number is 5% lower than estimated