X and Y together complete a task in 4 days, Y and Z together in 5 days. If they work independently, who will finish the work in the least time? A. X B. Y C. Z D. Not enough information to decide

Respuesta :

gami1234
gami1234 gami1234
  • 10-06-2020

Answer:

c, Z

Step-by-step explanation:

x+y=4

y+z=5

y=4-x

4-x+z=5

-x+z=1

z=1+x

Answer Link

Otras preguntas

As a slaveholder and a democrat president andrew jackson was
What's significant about the clothing that aunt alexandra hands to scout when she arrives home?
please help thank you very much
What are the characteristics of naturopathy? Check all of the boxes that apply.
On a map the distance between Atlanta,Georgia,Nashville, Tennessee, is 12.5. The Scale is 1in= 20mi. What is the actual distance between these two cities. —————
Help me catch up in Geometry? Thanks
Write the standard equation of the circle with center (-3, 5) and a diameter of 18.
Help please ASAP !!!
The_____could not hold back the flood.A. leveeB. leviC. levy
What happens after Farquhar seems to escape from the creek