A(n) _____ on a project is a significant event that normally has no duration. a. activity sequence b. milestone c. schedule baseline d. activity attribute

Respuesta :

Vickiee Vickiee
  • 14-03-2020

Answer: b. milestone

Explanation:

A milestone on a project is a significant event that normally has no duration. It often takes several activities and a lot of work to complete a milestone, but the milestone itself is like a marker to help in identifying necessary activities.

Answer Link

Otras preguntas

which of the two structure of school education system do you prefer the most and why​
Where in India dotropical evergreenand tropicaldeciduous forestsoccur? Name thestates:​
how are animals classified?​
Define matter Thanks!
Example of Mitochondria convert
This neurotransmitter is involved in learning. A: Serotonin B: Norepinephrine C: Acetylcholine D: GABA
How does water in Georgia play a role is its historical development and economic growth? Give two examples
Which is the best interpretation of the two flat portions of the graph?
Plzzz I’m giving a away 25 points
A resistor has code 104 printed on it .What is the resistive value of this resistor ​