a engineer has started to create a model in 27 days. 1/6 of the model is complete. how many days will it take to complete the model?

Respuesta :

kkelly69 kkelly69
  • 11-01-2020
It would take 22 1/2 days:

1/6 of 27= 4.5 days

4.5x5= 22.5
Answer Link

Otras preguntas

Factor out the coefficient of the variable 2/3 j - 2/9
What Is The Greatest Common Factor For 55,77 And 143
this is rounding off okay 454 by the nearest 10 what would it be 289 round it off by nearest 10 2,964 round off by nearest 10
what does the center of a dna strand exhibit
A 5.00 kilogram block slides along a horizontal,frictionless surface at 10.0 meters per second. for 4.00 seconds. The magnitude of the blocks momentum is ? A)20
Gary began peeling a pile of 44 potatoes at the rate of 3 per minute. 4 minutes later, Christen joined him, and peeled at the rate of 5 potatoes per minute. Whe
The circulatory system supplies the ______ to cells. water oxygen carbon dioxide nitrogen
this is rounding off okay 454 by the nearest 10 what would it be 289 round it off by nearest 10 2,964 round off by nearest 10
what does the center of a dna strand exhibit
plants use energy to absorb what?