If 4 electricians can complete a job in 8 hours how long will it take 3 electricians to complete the same job

Respuesta :

calculista
calculista calculista
  • 15-06-2018
we know that

if 4 electricians can complete a job in 8 hours
then
100% of a job -------> 8 hours
x------------------> 1 hour
x=100/8----> x=12.5%

divide by 4 electricians
12.5%/4-----> 3.125%
that means each electrician can complete 3.125% of a job in 1 hour

therefore
3 electricians-----> 3*3.125%----> 9.375% in 1 hour
so
9.375%-----------> 1 hour
100%--------------> x
x=100/9.375----> x=10.67 hours

the answer is
10.67 hours

Answer Link

Otras preguntas

Which equation below represents a proportional relationship between x and y A) y=x=90 B)y=-4x-5 C)y=1/7x D)y=4
please help me to solve this problem​
Describe the error(s)
Name examples of primary sources and secondary sources.
what two events turned the battle of horseshoe bend to Andrew Jackson advantage
What four ideas did the Council of Trent allow the Catholic bishops and cardinals to agree upon?
Hexabe is a hydrophobic solvent. 1) Which of the following would Hecate dissolve: A, B or C?
Which is an emotional consequence of engaging in sexual activity as a teen?
i inserted a picture of the question could you please make it short.
Adem and eve had 2 son kane killed able. where did kane wife come from? ​