In the above network diagram, assume each task takes one day. What is the total project time?
a. 6 days
b. 7 days
c. 4 days
d. 5 days

Respuesta :

Otras preguntas

"Why are you hating your job?" Correct the sentence
Your task is to write a story about WWII. Use outline below. Btwn 400 and 600 words in length. Be sure to include a creative element. This should read like a
6 x (1 + 2)=(_x1)+(_x2) what are the two missing numbers
Tony has an empty room in his house.The length of the room is 8ft. The width is 8ft,and the height is 10 feet.If he wants wallpaper all of the room,how many squ
4. Read the following sentence, changing the verb from the present tense to the preterite tense. Put the preterite form of the verb in the answer blank. Yo sé
What is the answer for #9?
Is unmake sensible a word if not than what is the opposite or the antonym of make sense
Is 9.59166304663 a rational or irrational number.
The second term of an arithmetic sequence is 7. The sum of the first 4 terms of the arithmetic sequence is 12. Find the first term, and the common difference, d
How are peptide bonds formed between amino acids in the elongation process of the translation of mRNA?