alexusjones1116 alexusjones1116
  • 08-05-2024
  • Mathematics
contestada

25person can finish a certain work in 20days.when should 15 persons leave the work ,if whole work to be finished in 37.5days after they leave work?​

Respuesta :

Otras preguntas

Which is an example of how bacteria help keep the environment clean?<<<
please help and thank you.
What is an ROI percentage useful for?
JB's music store is offering a 20% discount on all CDs and DVDs, meaning 80% of the price remains. If the discounted price of a CD is $16.80, then the original
How does Zlata Filipovic portray the people in her town?
simplify negative 9 plus 1/4xminus6minuz1/8z
Brian is a healthy young man. he has been training with his teammates for a 50yard dash for months. however, even with practice, he cannot run fast enough to qu
How might total warfare differ from other types of warfare
if a bag contains 12 apples, 4 bananas, and 8 oranges what is the part to whole ratio bananas to all fruit
what are the vertex and x-intercepts of the graph of y=x^2-4x-21?