For an activity in a CPM analysis, the Early Start time is 8 and the Late Start time is 10. Activity duration is 4 days. Which of the following statements is true?
A) The Late Finish is 14
B) The Early Finish is 12
C) Delaying this activity by 2 days will not affect project duration
D) A and B E) A, B, and C

Respuesta :

Otras preguntas

Why are some examples of a chemical reaction not actually foolproof evidence that of a chemical reaction?13, 8th grade, and I'm doing my science lab report: The
I need help for algebra 2 for simplify form for example (3x-2i)(3x+2i)
I need help for algebra 2 for simplify form for example (3x-2i)(3x+2i)
vesicles that contain a cells digestive enzymes are called ?
Why are some examples of a chemical reaction not actually foolproof evidence that of a chemical reaction?13, 8th grade, and I'm doing my science lab report: The
I need help for algebra 2 for simplify form for example (3x-2i)(3x+2i)
log3(2x-5)=2 Answer is 41/2.  Why?
log3(2x-5)=2 Answer is 41/2.  Why?
Alex built a snowman using three snowballs,one small, one medium and one large, with diameters in the ratio 2:3:5.      Although highly unlikely due to the phys
vesicles that contain a cells digestive enzymes are called ?