56 workers can finish a piece of work in 14 days. If the work is to be completed in 8 days, then how many extra workers are required?...

a. 36
b. 48
c. 44
d. 42
e. 32

Respuesta :

Marver1ck
Marver1ck Marver1ck
  • 08-02-2024

Answer:

e. 32

Step-by-step explanation:

14 days = 56 workers

8 days = x workers

We cross multiply and get:

14x = 448

x = 32 workers

So, the answer is e. 32.

Answer Link

Otras preguntas

What kind of letter is used to represent a recessive allele? A. Capital B. Lowercase
What type of structure are ionic lattices? Big structures Small structures Tiny structures Giant structures
A fully loaded and fueled spacecraft can weigh close to 4.6 million pounds. What is this weight converted to​ tons?
Given the inequality -8<2, explain what happens when you multiply or divide both sides by 2 and what happens when you multiply or divide both sides by -2.
What is the degree of the polynomial
Directions: Read the following advertisement. Think about the persuasive devices used in the advertisement, and then answer the following questions Attention te
Look at the pic below for the question please help!!
Liang Company began operations on January 1, 2012. During its first two years, the company completed a number of transactions involving sales on credit, account
How does anatomy provide evidence for evolution? I'll give brainlist!! Simple answer please.
If you have $50 in yo ur bank account, deposit a $50 birthday check, and withdraw $20 to buy a shirt, how much is left in your account at the end?