When a contractor is under a contractual duty to construct a building and the building is destroyed by an act of nature while it is still a work in progress, the destruction __________.

Respuesta :

imustapha180
imustapha180 imustapha180
  • 08-02-2020

Answer: the destruction will not discharge the contractor's duty to perform, but will extend the date of performance

Answer Link

Otras preguntas

acid rain is an example of____ a. a primary pollutant b. a secondary pollutant c. a tertiary pollutant d. none of the above
Please answer correct it is revision for my sats
Who signed the Atlantic Charter? a. Roosevelt and Hitler c. Germany and the Soviet Union b. France and Germany d. Churchill and Roosevelt The conquest of N
Which equation shows the substitution method being used to solv the system of equations? x+y=6 x=y+2 A. (y+2)+y=6 B. x+y=y+2 C. x=(x-6)+2 D. x+(y+2)=6
Select all that apply. To write a percent as a decimal, _____. move the decimal point two places to the left multiply by 100 move the decimal point two places t
What influenced the development of Byzantine art and architecture? A.Russian religious art was the major influence on Byzantine art. B.Egyptian and Indian art
Consumers drive the market using a. cost. b. price. c. supply. d. demand
Using 48 cubes, how many different rectangular prisms are possible?
Ben earns $9 per hour and $6 for each delivery he makes. He wants to make $155 in an 8-hour workday. What is the least number of deliveries he must make to reac
There are 4 cards with a picture of a rose and 3 cards with a picture of a daisy. Fiji keeps all the cards face down on the table with the pictures hidden and m