A 12 mile stretch of highway needs repairs. The work crew can repair 3/4 of a mile per day. How many days will it take to repair the damaged stretch of highway.

A 12 mile stretch of highway needs repairs The work crew can repair 34 of a mile per day How many days will it take to repair the damaged stretch of highway class=

Respuesta :

carlaedwards50ouwijf carlaedwards50ouwijf
  • 08-06-2019

Answer:

16 days

Step-by-step explanation:

  1. 12÷3/4
  2. 12/1÷3/4
  3. 12/1×4/3
  4. 4/1×4/1
  5. 16/1
  6. 16÷1
  7. 16
Answer Link

Otras preguntas

probability and statistics
5th out of 10 questions
Carcinogen is: when cancer spreads. a substance that causes cancer. a term that means the same as an aneurysm. the chemicals used to stop the spread
A poem that one of your classmates wrote about Abraham Lincoln is it primary or secondary ?
What is the measure of side YZ?
How was dholavira different from other most Indus cities
A line is the locus of points that: A. are the same distance from two points. B. are the same distance from one point. C. have the same sum of distanc
decide if the following change is an increase or decrease. then determine the percent of change. 48 inches to 30 inch
Identify in which word the apostrophe should be placed in the following sentence. Eight other families cars also need to be serviced ahead of ours.
What effects did the European arrival in America have on the native Americans