A road crew can repave 1/56 miles of road each hour. They must repave a road that is 7/8 miles long. How long will it take the crew to repave the road?

Respuesta :

wolf1728
wolf1728 wolf1728
  • 10-11-2018

7/8 miles = 49 / 56 miles so it will take the road crew 49 hours to repave the road.

Answer Link

Otras preguntas

1. As early as 100 B.C., during the Han Dynasty, Chinese traders were transporting goods along the Silk Road. Under the Tang Dynasty in the eighth and ninth cen
What is the digit in the one place is the sum of the digit in a dozon I know it is 12 but do I put it in on place value or the 2 or the 1 in the ones in place v
How many solutions are there to the equation y = 14x – 9? Plz HELP Explain your answer. A. There are no solutions because no value can be used for the varia
What is the digit in the one place is the sum of the digit in a dozon I know it is 12 but do I put it in on place value or the 2 or the 1 in the ones in place v
An organ system is made of many_________ working together to do a special job plz help
Single celled organisms are able to maintain internal stability because they
how did spain 's success in finding gold and land in the Americas affect other nations.
Solve. 4x + 4y = 20 4x + y = -10
25/10 as a mixed number
If a parallelogram has one right angle, what is the most descriptive name for it?